PROJECT- PSA Tuas Port Maintenance Base

The upcoming Tuas Port will be developed in four phases and terminal operations for the first phase is expected to start in 2021. As part of PSA Singapore’s sustainability plan to reduce carbon emissions, PSA is looking to develop green terminal buildings in the port.

Tuas Port Maintenance Base will consist of 8 buildings that serve various aspects of maintaining the port facilities. One of them being the 6-storey Administrative Building (under the Green Building Innovation Cluster Demo); this will be the first major building and the first Super Low Energy Building (SLEB) to be completed in Tuas Port. The building will house an operations centre which will manage all terminal operations for Phase 1 of Tuas Port, as well as a canteen, an engineering office and briefing rooms; expected to be ready in the fourth quarter of 2020.

Tuas Port Maintenance Base has hence adopted an Integrated Digital Delivery (IDD) approach in line with this effort that embarks on advanced info-communication technologies and smart technologies, integrating processes and stakeholders throughout all phases of port operations with a single source of truth.

PSA_Tuas_Port_Maintenance_Base

Image Credit: ID Architects Pte Ltd

Project Team:

  • PSA Corporation Ltd (Developer)
  • ID Architects Pte Ltd (Architect)
  • KCL Consultants Pte Ltd (C&S Engineer)
  • PDC Consulting Engineers (M&E Engineer)
  • GreenA Consultants Pte Ltd (Green Mark Consultant)
  • Chan Rong Fen Building Construction Pte Ltd (Main Contractor)

Project Highlights:

a. VDC Coordination in Virtual Reality
✓ One virtual collaborative space which allows multi-location & user coordination

b. Integrated and Automated DfMA Approach
✓ Shorter time and higher accuracy production planning through BIM

c. BIM Based Project Management
✓ Secured cloud data storage which allows viewing, navigating and accessing uploaded model information from multiple platforms

d. Defects Management Platform
✓ 20% improvement in managing defects via proper categorizing and organizing issues for easy identifications and follow ups

e. Safety Management Toolbox Meeting / Permit to Work / WHS Inspection
✓ 20% improvement with real-time implementation

f. Integrated Digital Assets Delivery & Management
✓ With BIM-Maximo Integration, which automates the migration of BIM data into Maximo, this will allow 20% efficiency improvements of the maintenance work planning and execution process

Popular e-Services

CWRS

The Construction Workforce Registration System (CWRS) is an online portal for CoreTrade and Multi-skilling registration and the renewal of Direct R1 eligibility.

Overseas Testing Management System

OTMS allows you to register the workers for Identity Verification and to check your registration status online.

Lifts and Escalators Application (LEAP) Portal

Lift and escalator owners, contractors and Specialist Professional Engineers (SPEs) can apply for and view applications for Permit to Operate (PTO) here.