×
!

Case Study - The Clement Canopy

ppvc banner

Project Team

Owner: United Venture Development (Clementi) Pte Ltd
Architect: ADDP Architects LLP
Structural Engineer: TW-Asia Consultants Pte Ltd
M&E Engineer: J Roger Preston (S) Pte Ltd
Main Contractor and PPVC Supplier: Dragages Singapore Pte Ltd

The Clement Canopy is a residential condominium located along Clementi Avenue 1. In its vicinity are three schools and residential blocks. The development has a Gross Floor Area of 50,200 m2, consisting of 505 dwelling units spread over two 40-storey blocks and a multi storey carpark with one basement floor. The basement floor, multi-storey carpark and first floor of the blocks are of conventional construction, while the typical floors from level 2 to 40 have adopted Prefabricated Prefinished Volumetric Construction (PPVC). 

The PPVC modules were designed as six-sided concrete PPVC modules. The weight of the modules ranged from 26 tons to 31 tons and were installed using two 48-ton capacity tower cranes. There were a total of 1,866 modules used in the construction of the two towers. The main contractor was able to install 10 to 12 modules per day with a floor cycle time of 7 days. The Clement Canopy is the world’s tallest concrete PPVC building. 

The adoption of PPVC at The Clement Canopy brought about many learning points in design, production and site works. Back in the design room, early confirmation of drawings and materials represented one of the major hurdles towards ensuring a smooth production cycle. Another of the early decisions to be made was the location of the heavy duty tower crane to determine the crane’s foundation and its tie-back to the main tower. This affected the overall structural design of the residential towers and modules had to be strengthened to cater for this additional loading. In addition, while quality of workmanship was improved as the bulk of architectural works were carried out in a factory controlled environment, strict site control and discipline had to be maintained to ensure minimal damages to the finishes. 

Overall, the adoption of PPVC has helped all stakeholders of the project in achieving shorter construction duration, higher quality workmanship, safer construction site and lesser disruptions to the surroundings schools.

tower crane hoisting of ppvc module

Tower Crane Hoisting of PPVC module

fit-out yard operations

Fit-out Yard Operations

grouting in between ppvc modules

Grouting in between PPVC Modules

completed residential units

Completed Residential Units

Popular e-Services

CWRS

The Construction Workforce Registration System (CWRS) is an online portal for CoreTrade and Multi-skilling registration and the renewal of Direct R1 eligibility.

Overseas Testing Management System

OTMS allows you to register the workers for Identity Verification and to check your registration status online.

Lifts and Escalators Application (LEAP) Portal

Lift and escalator owners, contractors and Specialist Professional Engineers (SPEs) can apply for and view applications for Permit to Operate (PTO) here.

TOP