Public shelters have to successfully pass commissioning tests before being issued a Notice of Approval of Commissioning (NOAC) and consequently, the Certificate of Statutory Completion (CSC).
Commissioning tests
Test |
To ensure that |
Internal overpressure test |
The external envelope of the public shelter guards against air leakage
|
Overpressure regime and airflow test |
The air supply system can regulate airflow through the ducts, dampers and CD valves in accordance with the functions and requirements of the shelter
|
Integrated systems test |
All systems in the shelter continue to function properly and reliably under normal supply when switching to the standby generator set
|
Detailed information on commissioning tests can be found in the
Handbook for Commissioning Requirements of Public Shelters.
Submissions to BCA
Item |
Method |
Method statements for tests and test reports |
Apply for approval by logging into the CORENET e-Submission System using e-form (BCA-CD_PLAN02.XFD) |
Notice of commissioning
(Book appointment to conduct Commissioning tests for Public Shelters) |
Notify BCA by logging into the CORENET e-Submission System using e-form (BCA-CD_NCOM01) |
Other tests
In addition to the commissioning tests, QPs must also conduct at various stages of construction:
- Air-tightness inspection
- Anchor bolts pull-out tests
- Individual function system tests
- Visual inspection of completed shelter
- CD door tests
- CD shock tests
Certificate of Supervision
In September 2024, BCA issued a Circular to inform the industry of the changes related to the Temporary Occupation Permit (TOP)/ Certificate of Statutory Completion (CSC) application for all development projects with Civil Defence Shelter (CD Shelter) including household, storey, public and transit shelters.