Application for Temporary Occupation Permit (TOP)

You need a Temporary Occupation Permit (TOP) or Certificate of Statutory Completion (CSC) to occupy a building.

Apply for a TOP when only certain requisites are complied with. When all the requirements are complied with, apply for the CSC for the building to be occupied on a permanent basis.

How to request for Joint Site Inspection

Steps

Description

How to apply

Qualified Person

  • log on the TOP/CSC Portal
  • select the project for TOP site inspection
  • select the date of TOP inspection
  • submit the Certificate of Supervision of Building Works (Form BPD_CSC02 or e-form BCA-CSC-CSPBW) and Declaration by Qualified Person for the Application of TOP/CSC for Building works
    (Form BPD_CSC07 or e-form BCA-CSC-CSCDQP)

3 days before the date of inspection

Express TOP inspection

Qualified Person

  • log on the TOP/CSC Portal
  • select the project for TOP site inspection
  • select the date of TOP inspection (up to the next 4 days from the date of application)
  • payment of $3000
  • submit the Certificate of Supervision of Building Works (Form BPD_CSC02 or e-form BCA-CSC-CSPBW) and Declaration by Qualified Person for the Application of TOP/CSC for Building works
    (Form BPD_CSC07 or e-form BCA-CSC-CSCDQP)
    3 days before the date of inspection

5. QP submits relevant documents

 

QP submits to the BCA the following certificates and documents: To remove entire para 5 because this section is only for inspection. 

  • Certificate of Supervision of Building Works (Form BPD_CSC02 or e-form BCA-CSC-CSPBW)
  • Certificate of Supervision of Lightning Protection System
    (Form BPD_CSC03 or e-form BCA-CSC-CSPLP)
  • Certificate of Supervision for Installation of Lift and Escalator
    (Form BPD_CSC04 or e-form BCA-CSC-CSPLE)
  • Certificate of Supervision of Mechanical Ventilation/Air-conditioning System
    (Form BPD_CSC05 or e-form BCA-CSC-CSPACMVS)
  • by Qualified Person for the Application of TOP/CSC for Building works
    (Form BPD_CSC07 or e-form BCA-CSC-CSCDQP)
  • Form BCA-BFA Checklist
  • Builder's Certificate of Completion of Building Works (Form BC/BC) or e-form BCA-BE-BRCTBW)
    Submit to the Building Engineering Department of BCA
  • Relevant forms and Certificates of Supervision for Structural Works. Submitted by PE under separate ES number to the Building Engineering Department of BCA
  • Certificate of Lift Maintenance and Testing
  • A copy of "Annex A"- Listing of Safety Barrier Submission
  • Submission of Record Plan
  • Notice of Acceptance of Commissioning from Civil Defence Shelter Engineering Department
  • QP's Declaration on Compliance with Daylight Reflectance for External Surface
  • Cable Readiness Certificate
  • To comply with the Building Control (Environmental Sustainability) Regulations 2008, submit at the Green Mark e-filing Portal the following forms:
    • BPD_GM01 (Green Mark score calculations for residential and non-residential buildings) at BP stage
    • BPD_GM02 (As-built Green Mark score calculations for residential and non-residential buildings) at TOP stage
  • Declaration by Qualified Person
    (Form BCA-CSC-TOPCSCDQP)
  • Certificate of Supervision of Building Works
    (Form BCA-CSC-CSPBW)
  • Certificate of Supervision of Lightning Protection System
    (Form BPD_CSC03)
  • Certificate of Supervision of Air-conditioning/Mechanical Ventilation System
    (Form BPD_CSC05)
  • A set of Barrier-free Access Route Plans, where applicable
  • Copies of Written Permission issued by the URA
  • As-built plans where any deviations from the approved building plans are highlighted
  • Other documents, if required by the BCA

How to apply for TOP

Requirements

  • Completed successful site inspection with BCA
  • Clearance from the following technical departments:
    • PUB – Drainage and Sewerage
    • NEA – Pollution Control and Environmental Health
    • FSSD – Fire Safety
    • LTA – Road & Transport
    • LTA – Vehicle Parking
    • LTA – MRTC line
    • NParks
    • URA
    • EMA (for residential development with 10 units or more)
    • Cable Readiness Certificate
    • CAAS and DSTA – Height Control

How to apply

 

Submit the following documents via CORENET e-Submission System:

  • Certificate of Supervision of Piling Works and Notice of Completion
    (Form BCA-BE-QPCTPW or BEV C1)
  • Certificate of Supervision of Structural Works
    (Form BCA-BE-QPCTSSW or BEV C2)
  • Certificate of Record Structural Plans/Calculations
    (Form BCA-BE-CTASST or BEV C3)
  • Builder's Certificate of Completion of Building Works
    (Form BCA-BE-BRCTBW or BC/BC)
  • As-built Plans, Test Reports and Certificate of Supervision of Lightning Protection System
    (Form BCA-CSC-CSPLP or BPD_CSC03)
  • Certificate of Supervision of Installation of Escalators/ Lifts/ Stair lift/ Platform lift
    (Form BCA-CSC-CSPLE or BPD_CSC04)
  • QP's declaration on compliance with daylight reflectance for external surfaces
  • Permit to Operate (PTO) for lifts in development 
  • Submission of Record Plan
    (Form BCA-BP-BPRP01)
  • Compliance to Written Advice issued after site inspection
  • Clearance on the as-built Buildability/ Constructability score
    (Form BCA-BP-BS03 or BPD_BS03, Form BEV-CS01)
  • Clearance on the as-built GM score
    (Forms BPD_GM02 + BPD_GM02_Appendix 2)
  • Commissioning approval for the CD shelters
    (Form BCA-CD-COMM01)
  • Declaration by Qualified Person
    (Form BCA-CSC-TOPCSCDQP)
  • Certificate of Supervision of Building Works
    (Form BCA-CSC-CSPBW)
  • Certificate of Supervision of Lightning Protection System
    (Form BPD_CSC03)
  • Certificate of Supervision of Air-conditioning/Mechanical Ventilation System
    (Form BPD_CSC05)

How to apply for Express TOP

The TOP can be obtained within one working day through Express TOP, a fast-track system.

Requirements

  • Meet all the TOP requirements
  • Compliance certificates from key technical departments or TOP/CSC for the works
  • QP confirms and certifies compliance with BCA requirements spelt out in the written directions from the BCA following the site inspection  

How to apply

Submit the BPD_ETOP application form through CORENET e-Submission System, after BCA confirms receipt of TOP application.

Fee

  • Major project: $1000
  • Minor project: $500 
workflow for advance booking system

Popular e-Services

CWRS

The Construction Workforce Registration System (CWRS) is an online portal for CoreTrade and Multi-skilling registration and the renewal of Direct R1 eligibility.

Online Registration for Verification System

ORV allows you to register the workers for Identity Verification and check your registration status online.

Online PTO System

Lift and escalator owners, contractors and Authorised Examiners (AEs) can apply for and view applications for Permit to Operate (PTO) here.