You need a Temporary Occupation Permit (TOP) or Certificate of Statutory Completion (CSC) to occupy a building.
Apply for a TOP when only certain requisites are complied with. When all the requirements are complied with, apply for the CSC for the building to be occupied on a permanent basis.
How to apply for Express TOP
The TOP can be obtained within one working day through Express TOP, a fast-track system.
Requirements
|
- Meet all the TOP requirements
- Compliance certificates from key technical departments or TOP/CSC for the works
- QP confirms and certifies compliance with BCA requirements spelt out in the written directions from the BCA following the site inspection
|
How to apply
|
Submit the BPD_ETOP application form through CORENET e-Submission System, after BCA confirms receipt of TOP application.
|
Fee
|
- Major project: $1000
- Minor project: $500
|